So, over the past few days, a lot of things have wrapped up. The electrician has everything roughed in and the plumber should be done with his first phase of everything tomorrow.
A timeline of our building experience with Wayne Homes in Greensburg, PA.
Tuesday, April 30, 2013
Tuesday, April 23, 2013
Alien Ant Farm
Today, and the past few days, have seen multiple contractors working at the same time. We have had the HVAC contractor, plumber, electrician and roofers in the past few days.
The roofers completed most of the first tier of the roof. I assume they'll finish up tomorrow as there is a lot less ground for them to cover tomorrow. |
Monday, April 15, 2013
Framing Day 5
Today, all the windows and exterior doors were placed with the exception of the sliding doors in the kitchen. I love it! It also looks as if everything is ready for shingles. Take a look!
We also got our Guaranteed Completion Certificate today! At the very latest, we'll be in by July 15! |
The front door in this picture is actually wrong. This should be the basement door. The front door is solid and is currently on the basement. |
Sunday, April 14, 2013
Framing Days 3&4
It's been a busy week so, thanks for your patience! On day three, they roughed out the interior second floor and add trusses...
Day 2
On day two, we had a few rough thunderstorms but they still got a lot done! They finished up the first floor and began work on the second!
Tuesday, April 9, 2013
Framing Day 1
Thursday, April 4, 2013
Catch up!
Hey there! Sorry it took so long to get this post up! The Friday before Easter week, the waterproofing was done. They did a great job!